Upcoming Water Corporation work on Hybanthus Road, Riverton

Home
News
Upcoming Water Corporation work on Hybanthus Road, Riverton
14 January 2025

Water Corporation, through licenced contractor Allpipe Technologies, will soon renew wastewater pipes on Hybanthus Road, Riverton.

The renewal of these ageing pipes is essential to prevent future blockages and extend the life of this important infrastructure by at least 50 years.

Work is planned to begin mid-January 2025 and is expected to be completed by the end of August 2025. Each section of pipe should take around three days in total to reline. Water Corporation will be in each area for a few hours at a time and may return to the area over several weeks

Work will be completed between Monday to Friday, 7am to 5pm and Saturdays as required. Water Corporation will notify residents if work is required outside these hours.

If your property is connected to the wastewater pipe being relined, Allpipe Technologies will provide you with further information 3-5 days prior to starting work.

For more information and exact work timings, please visit the Water Corporation website.